Specifying circular impact-absorbing surfacing is not a matter of adding the word “recycled” to a technical specification. You need to define a measurable requirement, check the safety of the complete system, ask for evidence of where the materials come from and organise acceptance checks. This method is aimed at clients, design consultancies, landscape architects and public buyers.

1. Define the use and the expected performance

Describe the site: playground, schoolyard or sports area; equipment installed; free height of fall; footfall; exposure to UV, frost and water; planned maintenance; type and condition of the substrate. These parameters determine the surfacing and its durability.

On public playgrounds, areas where children are likely to fall must be covered with suitable impact-absorbing materials. In France, the regulations also require a service life suited to the use, wear and climatic variations, together with hygiene and cleanliness requirements. Reference: decree no. 96-1136 on Légifrance (in French). Check the equivalent rules in your own country.

2. Describe performance, not a brand

The specification should set out the functions required: impact attenuation, fall height to be covered, drainage, slip resistance, surface continuity, wear resistance, colour fastness, repairability and maintenance. In public procurement, requirements must be linked to the need and proportionate; technical references should not restrict competition unnecessarily. Provide for equivalent solutions to be assessed against the same objective criteria.

3. Document the circular origin of the materials

The word “recycled” can cover very different realities. Distinguish materials from end-of-life products from industrial production offcuts, and ask for verifiable evidence:

  • Origin and traceability: type of material, geographical and industrial origin, processing site and batch identification.
  • Recycled content: claimed percentage by mass, scope and calculation method.
  • Consistency: tolerances on composition, grading, colour and mechanical properties.
  • Health and environment: relevant safety data sheets, regulatory declarations and test reports suited to the end use.
  • End of life: an actually available scenario for removal, collection, sorting, reuse or recycling, and the logistics involved.

Avoid general terms such as “eco-friendly”, “non-polluting” or “100% recyclable” without specific evidence. A recycled material never removes the need to demonstrate fitness for purpose and the safety of the finished product.

4. Compare material families

A poured-in-place surface can combine an elastic base layer and a top layer. SBR from tyres comes from an existing recovery stream; EPDM is a common synthetic top layer; granules can also come from industrial offcuts, for example from shoe-sole production. For each solution, ask for the origin, composition and documented performance.

Results must relate to the proposed configuration — base layer, top layer, binder, thicknesses, substrate and installation method — and not to a single component. A granule data sheet alone does not prove the performance of the finished system.

5. Require safety evidence and define acceptance

EN 1177 (2018 edition, amended by A1 in 2023) describes test methods for assessing the impact attenuation of playground surfacing in the laboratory or on site. Check the applicable standard reference when drafting the tender.

The specification should require: the reference fall height and impact areas on a plan; the composition and total thickness of the system; the relevant test reports; the post-installation testing procedure; the acceptance criteria; the expected test certificate; and the handling of non-conformities.

Do not settle for an “EN 1177 compliant” claim in a brochure. Check the scope of the report, the substrate, the thicknesses and how they match the installed system. References (in French): EN 1177+A1 – AFNOR and the DGCCRF practical guide.

6. Govern installation

Performance depends on substrate preparation, drainage, weather conditions, binder ratio, mixing and compliance with curing times. The specification should cover: checks on the bearing capacity, flatness, cleanliness and moisture of the substrate; verification of falls and drainage outlets; approval of samples; batch traceability; recording of laying conditions where necessary; protection during curing; and the time before reopening to use.

7. Plan for maintenance, repairability and whole-life cost

The price per square metre is not enough. Ask for a maintenance plan and look at the stated service life, local repairs, availability of replacement materials, cleaning, inspections and end of life. To compare bids, set common assumptions for the analysis period, transport, maintenance and renewal. Any claim of reduced impact must rest on a comparable method and data, ideally over the life cycle of the complete system.

8. Sample specification clause to adapt

Impact-absorbing surfacing incorporating circular materials: “The contractor shall propose an impact-absorbing surfacing system suited to the uses and fall heights shown on the drawings. The solution may incorporate materials from recycling or from the recovery of industrial offcuts. The bid shall state the origin and traceability of the materials, the claimed percentage by mass and its calculation method, the composition of the system, the thickness of each layer, the impact attenuation performance and the applicable test reports. It shall include the relevant technical data sheets and safety documents, installation instructions, tolerances, the maintenance plan, repair arrangements and the end-of-life scenario actually available. Any equivalent solution shall be assessed against the same functional, technical, health and environmental requirements. Acceptance shall include a document check and the tests defined in the contract on the completed works.”

This clause is a starting point: complete it with the fall heights, thicknesses, test criteria, timescales and acceptance conditions specific to the project. Have the file reviewed by the project designer and, where necessary, by a specialist in playgrounds and public procurement.

9. Specifier’s checklist

  • ☐ Uses, impact areas and fall heights defined.
  • ☐ Expected performance and measurable acceptance criteria.
  • ☐ Material origin, recycled content and traceability documented.
  • ☐ Test reports matching the complete proposed system.
  • ☐ Installation, site checks and acceptance planned.
  • ☐ Maintenance, repairs, service life and end of life described.
  • ☐ Verifiable, proportionate environmental criteria.
  • ☐ Equivalence and bid comparison organised without unjustified restrictions.

In summary

An effective specification turns the circular-economy objective into verifiable requirements: material origin, traceability, safety, durability, installation and end of life. An evidence-based approach is what makes it possible to compare bids and secure the project.

To find out more, see our pages on playground safety surfacing and Calzado, and our technical resources. Contact Terraludis Systems to discuss the material configuration and the technical documents to gather.

Planning a surfacing project?
We support public authorities, specifiers and contractors in designing surfacing systems that meet the relevant standards and technical requirements.
Request a technical study