A cracked, mossy or overly hard porous concrete court? Repaint it, overlay it with asphalt or apply a flexible resin: the three ways to renovate a porous concrete court, with their conditions and limits.
Thousands of tennis courts built in France between the 1970s and the 1990s are made of porous concrete, often called “Quick” courts after an old construction process. They drain well and are robust, but they age badly: the paint wears, moss takes hold, cracks open up and the surface stays very hard on the joints. When it comes to renovation, a club or municipality has three options.
Everything depends on the condition of the base. Before pricing anything, check:
This is the most common and the cheapest renovation: high-pressure cleaning, anti-moss treatment, then two coats of paint designed for porous concrete, which lets water through. The court gets its colours and line markings back.
Limits: the surface stays as hard as before, and the work has to be repeated every five to eight years. It does not deal with major cracks or with playing comfort.
Once the falls have been corrected and the perimeter drainage checked, a 40 to 50 mm layer of 0/6 asphalt is laid directly over the porous concrete. The court becomes an asphalt court, the reference base for poured sports surfaces, and then receives an acrylic resin, preferably with an elastic layer for added comfort.
This is the long-lasting renovation: the existing structure is kept, the court moves up a category and maintenance is then limited to repainting the finish. On the other hand, the court is no longer permeable: water runs off via the fall, which therefore has to be set correctly.
On a base that is sound, dry and free of open cracks, a resin system can be applied directly to the porous concrete, after high-pressure cleaning, anti-moss treatment and several passes of pore filler before the elastic layer.
This option avoids the asphalt, but it can only be decided after a survey: pore-filler consumption varies widely with how open the concrete is, and a sealed film laid on concrete that breathes can blister if moisture rises. A cracked or waterlogged court must be treated first.
For solutions 2 and 3, Terraludis offers Calzado Sport: an elastic layer made from shoe-sole offcuts, poured in 1 to 3 passes, under an acrylic tennis court finish. The system is 1.5 to 3 mm thick, keeps a ball bounce compliant with EN 14877 (97% measured by an independent laboratory) and cushions every step. The same surface can also take padel, pickleball, basketball or multi-sport line markings.
Terraludis carries out the study: a survey of the base from your photos, choice of solution and material quantities. In France, we then put you in touch with an installation contractor in your area; elsewhere, your own contractor carries out the work with our remote technical support. Pricing and execution of the works are the installation contractor’s responsibility.
Request a study · contact@terraludis.com · +33 6 70 67 74 43